Accelerated debrief in construction procurement
In December 2009, the Public Contracts (Amendments) Regulations 2009 came into force, which implemented the new Remedies Directive. The changes introduced had a significant impact on 'accelerated debrief' procedures which had been a means for tenderers to obtain information about an unsuccessful bid following contract award. From this they would then be able, if they so decided, to issue a challenge to the award.
Public contracting authorities must leave a period of least 10 days between a contract award decision and the formal award of the contract. This is known as the standstill (Alcatel) period. It is a legal requirement for all public contracting authority procurement processes covered by the full scope of the EU Procurement Directives.
The purpose of the standstill is to allow unsuccessful bidders the chance to obtain more information on the award of the contract so they can take appropriate action if they believe they have been unfairly treated. The commencement of the standstill (Alcatel) period is from the date the authority decides to award the contract. The standstill (Alcatel) period will last from 10 to 15 days, depending on the method by which the Alcatel letter is communicated.
The 2009 Remedies Directive removed the provision for an accelerated debrief and replaced it with an obligation for those awarding the contract to provide a more comprehensive statement concerning the reasons for the decision as part of the initial notice. This full debrief information accompanies all Alcatel standstill letters that are sent, not just to those bidders who request it.
Prior to these changes, unsuccessful bidders had to request an accelerated debrief by the end of the second working day of the standstill period. Responses to those requests had to be made within day 3-7 of the standstill period, with any delays resulting in a time extension.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
HBPT and BEAMS Jubilees. Book review.
Does the first Labour budget deliver for the built environment?
What does the UK Budget mean for electrical contractors?
Mixed response as business pays, are there silver linings?
A brownfield housing boost for Liverpool
A 56 million investment from Homes England now approved.
Fostering a future-ready workforce through collaboration
Collaborative Futures: Competence, Capability and Capacity, published and available for download.
Considerate Constructors Scheme acquires Building A Safer Future
Acquisition defines a new era for safety in construction.
AT Awards evening 2024; the winners and finalists
Recognising professionals with outstanding achievements.
Reactions to the Autumn Budget announcement
And key elements of the quoted budget to rebuild Britain.
Chancellor of the Exchequer delivers Budget
Repairing, fixing, rebuilding, protecting and strengthening.
Expectation management in building design
Interest, management, occupant satisfaction and the performance gap.
Connecting conservation research and practice with IHBC
State of the art heritage research & practice and guidance.
Innovative Silica Safety Toolkit
Receives funding boost in memory of construction visionary.
Gentle density and the current context of planning changes
How should designers deliver it now as it appears in NPPF.
Sustainable Futures. Redefining Retrofit for Net Zero Living
More speakers confirmed for BSRIA Briefing 2024.
Making the most of urban land: Brownfield Passports
Policy paper in brief with industry responses welcomed.
The boundaries and networks of the Magonsæte.